New and improvedThe new moveable barrier system offers considerable enhancements on the original. BY MARY SEARLE
The new barrier is made up of 2000 steel reinforced concrete blocks. At intervals along the barrier, 60 steel variable length units have been installed to absorb the geometric length changes in the barrier – not only does the barrier have to stretch or shrink as it is moved from one lane to another, the bridge itself expands and contracts with temperature changes. Narrower than the original, and with vertical as opposed to shaped faces, the new barrier gives vehicles an extra 20 centimetres of lane space. This may not seem like much, but the lanes on the bridge are narrow and any extra width is appreciated by motorists – allowing them to travel more comfortably at speed and giving them a little more room for error.
Martin Leak of Resolve Group, consultant to bridge owner NZ Transport Agency, and instigator of the original barrier 20 years ago, says the new barrier has been crash tested to both US and European standards (the European standard also includes buses). He says the new barrier, if hit by a car travelling at the speed limit of 80kph, would deflect as little as 300mm – a considerable improvement on the old barrier which would have moved around 600-700mm. “Both the barrier and the barrier transfer machine have a much higher safety spec than the old system,” he says. The new barrier transfer machines were manufactured by Barrier Systems Inc in California, the same company that designed the original ones. The technological improvements over the past nineteen years mean that the new machines are very sophisticated. Like the originals, the transfer machines are fitted with a line of rollers running in an S-shape underneath the machine that pick up the barrier units, shifting them across a full lane width before placing them down on the road again. “With the old machines, if you went too fast you’d end up with a ‘bow wave’ in the barrier in front of you until you got to a stage where you couldn’t move forward,” says Leak. “With the new machine, the transfer time has been more-than halved from over 45 minutes down to 20, and we have done a transfer in just 12 minutes!” This increase in speed is largely due to the size of the new transfer machine. At 15.5 metres they’re 3.5 metres longer than the originals so the tightness of the ‘S’ of rollers underneath is less pronounced allowing the barrier to be moved faster. The automatic guidance wires in the road (installed with the original barrier in 1990) allow the barrier to be placed in a consistent, accurate line. This in itself is further complicated by the shape of the bridge. Because the barrier is on a slope, when it is picked up gravity wants to pull it back down the sloping bridge deck. Electronically controlled capstan wheels on the transfer machine pull the barrier up the slope to counter gravity.
Other key improvements include:
When originally installed, the life for the two barrier transfer machines was estimated to be seven to 10 years. In actuality, they have seen 19 years of shifting 20 tonnes of barrier at a time every day before, finally, the maintenance costs outweighed the expense of new machines. Contractor, Auckland Harbour Bridge Special Supplement, May 2009 All articles on this website are copyright to Contrafed Publishing Co. Ltd. |