|
|
Site unseenPreserving the unspoiled Mullum Mullum Valley was the major consideration when deciding to build a traffic tunnel. BY ADRIAN GREEMAN
While it was expensive, those involved realised they had little option but to go underground to protect the environmentally sensitive Mullum Mullum Valley, an untouched area of wood and bushland in Melbourne. EastLink, the 39 kilometre toll road project on the eastern side of the country’s second biggest city, is aimed at easing increasing traffic congestion on existing roads. It opened in July last year. To deliver the route, the Victoria state government decided on the public-private partnership (PPP) approach. It set up SEITA (the Southern & Eastern Integrated Transport Authority) to oversee the work with ConnectEast as the concessionaire and the joint venture Thiess John Holland (TJH) as the contractor. It brought the already tight four-year programme home five months early with a host of extra works included along the colourful highway as well as specially commissioned artworks.
In engineering terms the $400 million tunnel was the most complex of the EastLink construction work and the largest single element, with various alignments being discussed. In the end, a 1.6 kilometre long alignment was chosen and that proved more expensive than thought on tendering. The project was completed in just three years following site build-up which started in February 2005. The first heading was excavated by August that year and breakthroughs occurred in October and November 2006. The tunnels were fully completed and operational in April 2008.
Les Bull, SEITA’s director of engineering for the northern half of the project, which included the tunnel section, says: “It was a pretty innovative design which simplified a rather complex cocoon-like arrangement in the initial scheme. I think it was better.” The move had cost advantages for the contractor; was favourably received by local residents after they had seen various 3-D visualisations and, importantly, it also had construction advantages. Construction work required almost continuous 24-hour working to be economical and to match the fast pace of work on the rest of the road.
The 70 metre long ventilation buildings, which span across both parallel tunnel bores, were used to stockpile a night’s worth of the rock cuttings and fragments carved out at the tunnel face and from the benches that followed on behind. Next day they were removed by trucks along with the cuttings coming off the day shift excavation. The spoil was produced by four large roadheader machines, which have rotating toothed heads on the end of large booms. They were used to cut the rock rather than tunnel boring machines (TBMs), which would have proved costly.
The roadheaders were fitted with scoop arms at the front and conveyors at the back, and this meant easy loading straight into the 35 tonne articulated dump trucks TJH used for moving the spoil. Using the roadheaders also meant cleaner cutting as their computerised controls could form the top heading of the tunnel with close precision and little overbreak. However, at some points the rock became too hard, and here drill and blast had to be used. A boomer was moved up to drill the holes pattern for blasting, although times for this were restricted and special measures were taken to inform people in the vicinity. Once a six metre deep top heading was done by either method the rest of the tunnel depth was removed in benches using excavators fitted with hydraulic breaker hammers.
The tunnel was also required to be fully ‘tanked’, or watertight, rather than allowing water in and draining it out, and to achieve this meant having a rounder cross section for the tunnel and using a membrane lining sealed behind a permanent inner concrete lining. Installing a membrane without damage is particularly difficult on the bottom of the tunnel, so a fleece was used behind the membrane to protect it from the rough shotcrete. To prevent workers fitting reinforcement from treading on the membrane, the contractor devised a system of precast curved floor units 8eight metres wide and two metres long, which were installed either by a small crane or with a purpose-built gantry. The units were transported into the tunnel by a specially made up frame modification to the dump trucks. They sat on two temporary blocks on the membrane and were then grouted in. A flat top to the unit allowed trucks to run by, and two edges took temporary rails on which a large gantry could be supported. There were two gantries for each tunnel, one a set of platforms from which the rest of the fleece and membrane could be installed and welded to the floor and already installed wall sections.
For the cross passages between the two tunnel bores (every 120 metres), required in case of fire or other disaster, the excavations were started from the top headings and finished using a fifth roadheader. A complex piece of formwork was used to block them out as the main form passed so that the reinforced openings could be made as part of the main wall, with the insides finished later. During construction the passages were used so that dump trucks could pass between the bores: one as a “dirty” haul tunnel and the other for “clean” concreting. Once the tunnel lining was completed the curved invert was backfilled to road level using the spoil from the still continuing faces. In this new platform a trench was made for drainage and the multiple electrical and communications cables needed in a modern tunnel.
Contractor Vol.33 No.2 March 2009 All articles on this website are copyright to Contrafed Publishing Co. Ltd. |