|
|
Cliff top challengeThe Ohope Escarpment Drainage project was a small but technically challenging project that required an innovative and collaborative approach between the local authority, consultant, contractors and community to solve a long-standing problem of slope stability.
HEB Construction was engaged to undertake the $2.76 million project, which began in September 2007 and was completed in May last year. Project manager David Burns says the project posed a number of challenges.
Wastewater from the properties at the top of the escarpment (which were previously using septic tanks) was routed through the drilled pipelines to an existing wastewater sewer serving properties at the foot of the cliff. In total, the project involved 9.4 kilometres of pipelines, of which about half were public lines and the rest private connection pipework.
The longest directional drill was 244 metres long through rock with a strength of up to 100MPa, using a 250mm drill to then install a 180mm diameter pipe with a fall of over 90 metres. And this is where the next big challenge presented itself to the contractors. “With the directional drilling in excess of 50 metres, the sensor couldn’t be picked up – so we were drilling blind for about 100 metres,” says David Burns.
“This was a major achievement considering we couldn’t see the drill for nearly half of it,” says Burns. Along the roadside, the trenches were open cut. To allow traffic to continue using the road the spoil was trucked away from the trench. Another challenge, a health and safety one, arose because a lot of work was on the top of the escarpment – the contractors were working on or adjacent to a cliff face that was a minimum of 45 metres high and comprised unstable ground which was susceptible to further movement.
Another major aspect of this project was the very high level of stakeholder involvement and community support that was generated under tight time constraints. Through good early consultation, stakeholders recognised the benefits of a joint approach to the problem and were quickly committed to the projects. By eliminating on-site stormwater and wastewater soakage, and reducing stormwater runoff, the stability of the escarpment has been improved significantly. This has provided greater security for Ohope, improving safety for the local community as well as enhancing the environment.
The project has been strongly praised by all involved and recently netted Tonkin & Taylor a merit award at the Association of Consulting Engineers (ACENZ) Innovate NZ awards. Contractor Vol.33 No.8 September 2009 All articles on this website are copyright to Contrafed Publishing Co. Ltd. |