|
|
Strength, grace and economyIt’s the first bridge of its type built in New Zealand, and it saved a bundle of dollars on a conventional structure. HUGH DE LACY reports.
The network arch bridge design was pioneered by Dr Per Tviet in the 1950s, and when the man himself came to New Zealand in October 2007 for a seminar hosted by the Heavy Engineering Research Association (HERA), Phil Gaby of the Wellington branch of the Holmes Consulting Group was there to hear what he had to say. What Tviet described was an arched bridge in which the hangers supporting the lower tie were not strung vertically, but at an angle of between 50 and 70 degrees. They crossed each other at least twice, distributing the bending moments and shear forces to the arch at the top, and to the tie – the roadway, railway or footpath – at the bottom.
The first network arch bridge was built at Steinkjer, Norway, in 1963, and quite a few have been built in Japan, but uptake of the design has been relatively slow elsewhere. Gaby told Contractor he had no New Zealand application in mind for a network arch bridge when he attended the HERA conference, but its relevance to the Mangamahu situation struck him when he first began to look at that project. “I expected neither the contractor nor the client to want to take the risk [of a new design], but they were both all go,” he says. The $2 million contract went to the Rotorua company Concrete Structures, whose general manager and owner, Mike Romanes, was undaunted by a design requiring only 150 cubic metres of concrete to go with the 80 tonnes of structural steel.
The council’s specimen design had envisaged two 42.5 metre spans with a central pier in the middle of the river, and a deeper superstructure that would have required the approach roadway to be raised to keep the soffit of the replacement bridge at the same level as the previous one. Significant flood protection works would also have been required for both the riverbank and the pier. The 47-year-old original bridge, which collapsed two days after the flood, had three spans supported on raked piles, with wall-type piers and twin steel I-girders made composite with a concrete slab deck.
The key to the rapid construction, which features a steel-weight to bridge-area ratio of just 150 kilograms per square metre, was that much of it was conducted off-site. “It was more of an assembly operation than a construction,” Romanes says. The steel ladder deck was supported on falsework at spans of about 30 metres, while the arch was split into halves assembled on either side of the river. The 32 parallel hangers were angled at 60 degrees and constructed of standard off-the-shelf 32mm diameter Reid bars.
Once the hangers had been installed, the decking falsework was removed and the pre-cast decking panels lifted into place to provide a permanent formwork for the in situ concrete topping. The design might have been a New Zealand first, but Romanes says it was simplicity itself to execute. “We never even used a gas-set on the site, and every bolt fitted in every hole.” He had just two men working on the foundations and the abutments, and six more assembling the arch and constructing the deck.
Introducing the new construction system to New Zealand required extensive pre-design analysis, including building a three-dimensional model. “It was a traditional design process but it was quite sophisticated because this hadn’t been done before,” Gaby says. “We analysed each hanger, each arch segment, bottom cords and transfer transoms. Their load paths all interconnected so we had miles and miles of load cases for miles and miles of different members, but we set the thing up and automated it as much as we could with spread-sheets connected to the analysis.”
In fact the country may not have to wait long for a second such bridge: a Holmes Consulting Group design for a two-lane 100-metre network arch bridge is presently being constructed for the Taupo arterial route. Contractor Vol.33 No.8 September 2009 All articles on this website are copyright to Contrafed Publishing Co. Ltd. |