|
|
The cementing of Pike RiverThe supply of high performance concrete for the isolated Pike River coal tunnel project had its challenges, says Concrete Society president Chris Munn.
Developing the access tunnel to a seam of high quality coking coal located under Department of Conservation land, 50 kilometres inland from Greymouth, has been a two year project that is due to finish this month (December 2008). The export resource is 58 million tonnes, and almost 20 million tonnes of this is recoverable. The access tunnel is 2.3 kilometres long and inclines at a grade of one in 11, and is 5.5 wide and 4.5 metres high. At the time of Chris Munn’s presentation at this year’s concrete conference, the tunnel project had reached over 2.1 kilometres in length and involved over 5000 cubic metres of special concrete supplied by Allied Concrete from its batching plant at South Beach near Greymouth, some 75 kilometres away. The environmentally sensitive area and the special concrete mix for lining the tunnel, had its unique challenges, says Chris Munn, who is the national technical manager at Allied Concrete. “Concrete was supplied on a 24 hour, seven-day basis using three shifts,” he says. “Site placement procedures required the concrete to be retarded for up to 13 hours prior to use at the tunnel face.”
“Immediately after the first full face blast in mid September 2006, it became apparent that there would need to be a rapid re-evaluation of the tunnelling methodology.” Because of the poorer rock conditions one to two metres beyond the “outer shell” of the parent rock, the entire project’s allocation of rock bolts and galvanised mesh were consumed in the first three month’s work. Instead of a largely self-supported tunnel, the rock’s properties and dense fracture patterns in the gneiss were such that large amounts of shotcrete were required for the long term stability of the tunnel. Initial shotcreting was by the dry process, supplied in bulk loads from Allied’s batching plant at Greymouth and applied over weakened areas of rock that was reinforced with galvanised mesh. “This operation was slow and also required significant volumes of shotcrete to be applied due to over-break.”
“This would enable concrete to be used at short notice if the tunneling operations encountered soft rock at any stage during the 24 hour operations.” The material was also to be fibre reinforced using polyolefin type structural fibres, as used on the Northern Gate Project in Auckland where Allied Concrete was also involved. The concrete was to have a nominal strength of 40 MPa based on cores taken from test panels made on site, or taken from selected locations within the tunnel, rather than based on traditional QA systems. The remote shotcrete machine arrived in January 2007 and came straight out of the box for initial trials at the Allied concrete plant in Greymouth using existing concrete mix designs. “In my experience, you always run into strife using equipment straight out of the box.” The problem was the concrete mix – it had to have a very high slump of 200mm, and it also had a high air content because of the reinforcing plastic fibre, and very fine sand – which lead to pumping issues.
Extensive trials extended over a period of several weeks, involving consultation with Sika’s research laboratory in Zurich, resulted in a final mix design contained significantly higher proportions of aggregate than would normally be used to counter the impact of the relatively fine sand. The mix is made up of concrete, water and eight other ingredients that Allied is keeping to itself. “We ended up with a well-constituted concrete mix that could be sprayed on the tunnel walls from between five and 10 metres away, and were presented with no problems.” By the end of September this year, under very trying conditions, over 4000 cubic metres of concrete had been delivered to the remote site and used successfully in the tunnel. “And only one load was rejected,” says Munn. “I think that is pretty good going.”
Q&M Vol.5 No.5 December 2008 - January 2009 All articles on this website are copyright to Contrafed Publishing Co. Ltd. |